How long does it take to arrange a new gas or electricity meter?

There are many factors that can affect how long it takes to arrange a new meter. If everything is lined up and ready then a new meter can be supplied within 15 working days, although it may take up to 20 days. It’ll then take 3 working days for the registration of the supply and an additional 10 working days for a meter installation date. This process is the same regardless of whether it is a gas or electricity meter.

Using amber energy to help install new meters can help to accelerate this process, learn more about our new meter connections service here.